Monday, May 25, 2015

Road Construction Update

Week of May 25th:
Installation of drainage structures and pipe (starting at Arcadia and heading south along West St)
Installation of utility poles throughout project
 
Week of June 1st:
Continue installation of drainage structures and pipe (projected to end near Palmer Hill Ave.)
Continue installation of utility poles and transferring cable throughout project
 
Week of June 8th:
Continue installation of drainage structures and pipe (projected to end near King St.)
Continue installation of utility poles and transferring cable throughout project
 
Weather-permitting
 
NOTES:
-The Summer Ave-Woburn St detour will be used during normal work times (7am-3pm)
-Northbound school traffic will be detoured to King St-Summer Ave to access Arcadia from the north.  All Edgemont St traffic will have to turn south on West St until Newport is beyond Edgemont; then Edgemont traffic will have to turn north on West.
 